Comprehensive List of Approvals, checklist, Procedures & Timelines


Sr. No. Department Name Form Name Time Lines (in days) Category View

1

Labour Department

Registration and grant and renewal of license under The Factories Act, 1948

30 days from the date of application

Pre-Establishment

VIEW

2

Approval of plan and permission to construct/extend/or take into use any building as a factory under the Factories Act, 1948

30 days from the date of application

Pre-Establishment

VIEW

3

Registration and Renewal of Boilers under The Boilers Act, 1923

30 days from the date of application

Pre-Operation

VIEW

4

Approval for Boiler manufacturer and renewal thereof

30 days from the date of application

Pre-Operation

VIEW

5

Approval for Boiler erector and renewal thereof

30 days from the date of application

Pre-Operation

VIEW

6

License and renewal of license for contractors under provision of The Contracts Labour (Regulation and Abolition) Act, 1970

3 weeks from the date of application

Pre-Operation

VIEW -1
VIEW -2

7

Registration and renewal under The Shops and Establishment Act

3 weeks from the date of application

Pre-Establishment

VIEW

8

Registration of principal employer's establishment under provision of The Contracts Labour (Regulation and Abolition) Act, 1970

3 weeks from the date of application

Pre-Operation

VIEW

9

Registration under The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996

60 days from the date of application

Pre-Operation

VIEW

10

Registration of establishment under the Inter State Migrant Workmen (RE&CS)Act,1979

3 weeks from the date of application

Pre-Operation

VIEW

11

Housing Department

Building Plan Approval

90 days

Pre-Establishment

VIEW

12

Forest Department

NOC for tree felling from Tree Authority/ Appropriate Authority (prior to commencement of construction activities)

15 days of the date of submission of the forms

Pre-Establishment

VIEW

13

Fire Services

NOC for Fire Department (prior to commencement of construction activities)

15 days of the date of submission of the forms

Pre-Establishment

VIEW

14

Pollution Control Board

Consent to Establish under the Water (Prevention and Control of Pollution) Act, 1974

Within 120 days of the date of submission of the forms

Pre-Operation

VIEW

15

Consent to Establish under the Air (Prevention and Control of Pollution) Act, 1981

120 days of the date of submission of the forms

Pre-Operation

VIEW

16

Authorization under the Hazardous and Other Wastes (Management and Transboundary Movement) Rules, 2016

120 days of the date of submission of the forms

Pre-Operation

VIEW

17

Consent to Operate under the Water (Prevention and Control of Pollution) Act, 1974

Within 120 days of the date of submission of the forms

Pre-Operation

VIEW

18

Consent to Operate under the Air (Prevention and Control of Pollution) Act, 1981

Within 120 days of the date of submission of the forms

Pre-Operation

VIEW

19

Stamp and Registration

Property Registration-Online systems

1 day

Pre-Establishment

VIEW

20

Urban Development

Obtaining water connection

30 days of the date of submission of the forms

Pre-Operation

VIEW

21

Food Safety and Drug Administration

Retail Drug License (Pharmacy) and renewal thereof

30 days of the date of submission of the forms

Pre-Operation

VIEW

22

Wholesale drug license

30 days of the date of submission of the forms

Pre-Operation

VIEW

23

Weights and Measures

Registration and renewal under the Legal Metrology Act, 2009

45 days of the date of submission of the forms and 30 days of the date of submission of the forms

Pre-Operation

VIEW