Approvals for Entrepreneurs


Department Name Sr. No. Form Name Time Lines (in days) Fee Details
Labour Department 1. Registration under UP Shops & Establishment Act, 1962 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
2. Renewal under UP Shops & Establishment Act, 1962 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
3. Approval of plan and permission to construct/extend/or take into use any building as a factory under the Factories Act, 1948 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
4. Registration and grant of license under The Factories Act, 1948 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
5. Renewal of license under The Factories Act, 1948 60 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
6. Registration of Boilers under Indian Boillers Act, 1923 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
7. Renewal of Boilers under Indian Boillers Act, 1923 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
8. Approval of Boiler Manufacturer 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
9. Renewal of Boiler Manufacturer 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
10. Approval for Boiler erector 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
11. Renewal for Boiler erector 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
12. Registration of principal employer's establishment under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
13. License for contractors under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
14. Renewal of license for contractors under provision of The Contracts Labour (Regulation and Abolition) Act, 1970 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
15. Registration under Motor Transport Act No statutory timeline yet. Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
16. Renewal under Motor Transport Act No statutory timeline yet. Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
17. Registration under Beedi Cigar Act No statutory timeline yet. Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
18. Renewal under Beedi Cigar Act No statutory timeline yet. Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
19. Registration of establishment under the Inter State Migrant Workmen (RE&CS) Act, 1979 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
20. Renewal of establishment under the Inter State Migrant Workmen (RE&CS) Act, 1979 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
21. Registration under The Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996 30 Submitted in Phase 1. Fee is calculated by the department based on inputs in the form.
Stamps and Registration 1. Property registration 1 day (from date of appontment) Phase 1: Calculator
Pollution Control Board 1. Consent to Establish Under Air and Water Act(NOC) 120 Fee needs to be calculated
2. Consent to Operate Under Air Act 120 Fee needs to be calculated
3. Consent to Operate Under Water Act 120 Fee needs to be calculated
4. Hazardous Authorization 120 No fee is required
Revenue Department 1. Change of Land Use 45 Days Fee needs to be calculated
Fire Department 1. Completion of NO OBJECTION CERTIFICATE of Fire Service 15 No fee is required
2. Renewal of NO OBJECTION CERTIFICATE of Fire Service 15 No fee is required
3. NOC from Fire Department (prior to commencement of construction activities) or Provisional 15 No fee is required
Power Corporation Limited 1. Power Connection 30 days Phase 1: Calculator
Phase 2: Calculator
Forest Department 1. NOC for Tree Felling 15 Fee needs to be calculated
2. Tree Transit permission 15 Fee needs to be calculated
PIC UP 1. Application form for sanction of incentives for Small, Medium & Large Industrial Undertakings 30 Days No Fees
2. Application form for disbursal of incentives for Small, Medium & Large Industrial Undertakings where Letter of Comfort(LoC) has been issued 30 Days No Fees
3. Application form for sanction of incentives vide Letter of Comfort for Mega, Mega Plus and Super Mega Industrial Undertakings 30 Days No Fees
4. Application form for disbursement of incentives for Mega, Mega Plus and Super Mega Industrial Undertakings 30 Days No Fees
Legal Metrology 1. Application for the issue of new licenses to the Manufacturer 45 Days
2. Application for issue of New License to Dealer 30 Days
3. Application for issue of New License to Repairer 30 Days
4. Renewal for the issue of new licenses to the Manufacturer 30 Days
5. Renewal for issue of New License to Dealer 15 Days
6. Renewal for issue of New License to Repairer 15 Days
Electrical Inspectorate 1. Initial inspection of Generating Set 20 days Phase 1: Calculator
2. Initial Inspection of Low Pressure Installation 20 days Phase 1: Calculator
3. Initial Inspection of Medium Pressure Installation 20 days Phase 1: Calculator
4. Initial Inspection of High / Extra High Voltage Installation 20 days Phase 1: Calculator
Phase 2: Calculator/based on findings
Food Safety and Drug Administration (Drug) 1. For Wholesale licence 15 1500
2. For Retail Licence 15 1500
3. For Restricted Licence 15 500
4. For Drugs specified in Schedule-X(Wholesale) 15 500
5. For Drugs specified in Schedule-X(Retail) 15 500
Food Safety and Drug Administration (Food) 1. Application for License/Renewal of License under Food Safety and Standards Act,2006 30 Fee needs to be calculated
2. Application for Registration/Renewal of Registration under Food Safety and Standards Act,2006 15 Fee needs to be calculated
Industrial Development Authority - UPSIDC 1. Pre-Allotment/Land allotment 21 Days Fee needs to be calculated
2. Pre-Allotment/Land allotment
Industrial Development Authority - NOIDA 1. Building Plan Approval 60 Days Fee needs to be calculated
2. Land allotment system 45 Days Fee needs to be calculated
Industrial Development Authority - GREATER NOIDA 1. Building Plan Approval 30 Days Fee needs to be calculated
2. Land allotment system 45 Days Fee needs to be calculated
Industrial Development Authority - UPYEA 1. Building Plan Approval 15 Days Fee needs to be calculated
2. Land allotment system 21 Days Fee needs to be calculated